UPDATE: NUCLEAR CASE POSTPONED TO FEBRUARY 2017 – GOVERNMENT ORDERED TO PAY PUNITIVE COSTS On 13 December 2016, the Western Cape High Court postponed the challenge by Environmental Justice Groups Earthlife Africa Johannesburg (ELA-JHB) and the Southern African Faith Communities Environment Institute (SAFCEI), to the legality of the government’s nuclear procurement deal. In doing so, the Court ordered the Minister of Energy to pay the applicants’ costs on a punitive scale, including the costs of four counsel.

The importance of the challenge is clear: it relates to the largest procurement deal the country has seen since the advent of democracy, a deal which is feared to have been engineered for Russia to be the preferred bidder.

In what the Court described as a “disquieting” twist of events, court proceedings began with the senior counsel for the State (Marius Oosthuizen SC) announcing that yet another secretive Section 34 Determination for nuclear power had been signed by the current Minister of Energy, Tina Joemat-Pettersson.

Despite it being signed on 5 December 2016, the Court was not informed thereof and neither were the applicants – until literally minutes before the hearing was to begin. The Court stressed in its judgment that there was no evidence presented to the court explaining how this determination came about, when it was decided upon and the processes leading thereto, despite the Determination apparently having been made more than a week before the hearing.

The state’s legal team also argued that the Department of Energy is no longer the procurer of nuclear power but that this responsibility has now been handed over to Eskom, which the State argues is a company with its own board and therefore requires no mandate and no consultation from the state or the public to carry out its business and the spending of public funds.

At the very time that the parties were arguing in court, the media reported that the request for proposals for the procurement of nuclear energy was to be released this week.

Project Coordinator at Earthlife Africa Johannesburg, Dominique Doyle, argues that “this was in fact, nothing short of an insidious delay and divide tactic on behalf of the Department of Energy, Eskom and NERSA. Instead of arguing the legalities and constitutionality of the Determination made in 2013 and then kept secret for 2 years, the courts were forced to deal with this latest development.”

After hearing arguments, and despite the State’s advocate arguing that it should not be ordered to pay punitive costs, the Court expressed its displeasure with the State’s conduct by ordering that the State should pay the costs of the applicants’ four counsel and on a punitive scale.

The Judges made it clear that the case needed to be heard on an expedited basis, and the case has been adjourned for hearing on 22 to 24 February 2017.

Spokesperson for SAFCEI, Liz McDaid says, “Democracy depends on transparent and accountable government decision-making processes. We are looking forward to seeing justice done when we get to court in February next year.”

For more information, go to the SAFCEI website (http://nuclearcostssa.org/), the Facebook page (https://www.facebook.com/SAFCEI/), or contact their offices directly on 021-701-8145 or email info@safcei.org.za.

Or to the Earthlife Arica Johannesburg website (http://earthlifeafrica.org.za/), the Facebook page (https://www.facebook.com/earthlifeafricajohannesburg/) or contact their offices directly on 011-339-3662.

ENDS

Issued by Natasha Adonis on behalf of Earthlife Africa Johannesburg, the Heinrich Böll Foundation and SAFCEI. For more information, please contact me on 0797 999 654 or email adonisnatasha@yahoo.co.uk